Descrição do projeto
Technical task for projecting the hull
Background:
1. Road travel plan between two factory buildings with indication of wells of engineering networks, including: Drainage, as well as slabs and drainage trays.
2. Marks of road plates after removal of repair coating (start surface), marks of drainage wells, drainage tray.
Purpose:
Create a mound (a screed of mineral repair composition), at least 20 mm high and not more than 40 mm with slopes to drainage wells and a tray for water drainage and the exclusion of puddle formation with the minimum possible volume of embankment. Drainage wells can be lowered below to provide drainage.
Task:
1. Create a mound project (knees from mineral repair composition), at least 20 mm high and not more than 40 mm with slopes to drainage wells and a tray with the minimum possible volume of embankment.
2. Determine the area and volume of the mound.
3. Determine the maximum, minimum and average height of the mound.
4. The surface of the mound should not contain closed local lowered areas (puddles).
5. It is allowed to lower the drainage wells.