Елена
Employer

[no-member:pro]Елена[/no-member:pro]Елена

3 projects
Closed
Project parameters
Type of cooperationOne-time project
Prepaymentwithout prepayment
Payment methodsBank transfer
Acceptance of requestsclosed
Project description
Offering remote work for the designer. It is necessary to perform working documentation for the project "Data Center Design"
The object of development is the premises allocated for a data center (hereinafter - the data center) with an area of 39.46 sq.m.
The location of the data center is planned on the 1st floor of the newly built building
The following equipment is placed in the data center premises:
- IT cabinets;
- switchboard cabinets;
- cabinets of active network equipment;
- climatic equipment;
- uninterruptible power supply system;
- automatic gas fire extinguishing system.

Composition of working documentation:
- a general explanatory note;
- the project of organization of construction;
- installation structures (false floor, construction of insulation of a hot corridor, trays, cabinets);
- power supply system, uninterrupted power supply, lighting, grounding and potential alignment system (performed by the Customer);
- air conditioning and ventilation system;
- security systems;
- automatic gas fire extinguishing system (performed by the Customer);
- a structured cable system;
- control system and interactive control of engineering systems;
- program and method of testing of the power supply system (performed by the forces of the Customer);
- program and method of testing of ventilation and air conditioning system;
- program and methods of testing of safety systems;
- program and method of testing of fire extinguishing system;
- a comprehensive program and test methodology;
- private technical task for the construction preparation of the data center;
- private technical task for the organization of power supply and grounding (performed by the Customer);
- private technical specification for the supply of external communication lines, communication lines and algorithm for interaction of enterprise security systems and data centers;
- estimate documentation.

Each volume of the working documentation should contain the following interrelated documents for each system and/or subsystem:
Structural, single-line and principled schemes;
- the main technical solutions and schemes;
- Plans of premises with the placement of equipment;
- incisions;
- cable logs;
- specifications.
Project author: Елена